Skip to contentUnited States Department of Transportation - Federal Highway Administration

International

 

Risk Assessment and Allocation for Highway Construction Management

Risk Management Matrix - High Probability, High Impact

Return to Text

chart

Figure 22. WSDOT cost and risk status report on the I-405 Congestion Relief and Bus Rapid Transit Projects, revised July 2003. The report contains the following:

Scenario: Tukwila to Bothell (Option C)

Project descriptions:
  • Continuous multimodal corridor improvement projects from I-5 in Tukwila to SR-522 in Bothell.
  • Adds one lane each direction from I-5 to SR-181 in Tukwila.
  • Adds two lanes each direction from SR-181 in Tukwila to I-90 in Bellevue.
  • Adds one lane each direction from I-90 in Bellevue to SR-522 in Bothell.
  • On SR-167, adds one lane between I-405 and South 180th Street.
  • Constructs bus rapid transit system with stations, H-O-V direct access ramps, and park-and-ride lots and coaches.
  • Expands the vanpool program.
Project benefits:
  • Reduces congestion and improves freight movement.
  • Provides bus rapid transit system from SeaTac to Lynwood.
  • Constructs 2,300 new park-and-ride spaces.
  • Adds 600 new vanpools and increases commute reduction programs.
  • Improves water resources.
Project risks:
  • Changing environmental requirements for project mitigation (storm water, wetlands, fish resources, and streams) may increase project costs-primarily for added right-of-way purchases.
  • Delays in right-of-way purchases may result in construction delays and project cost increases.
  • Early stage of project development leads to scope uncertainty.
  • Legal challenges and delays in obtaining environmental permits may result in project delay.
  • Utility relocations may require extra time to negotiate and complete.
Schedule:

Begin construction in 2006-2007 and end construction in 2013-2014.

Project cost range:

A Cost Estimate Validation Process graph shows probability on the y-axis and total project cost in future dollars on the x-axis. There is a 10 percent chance the cost will be less than $4.2 billion, a 50 percent chance the cost will be less than $4.7 billion, and a 90 percent chance the cost will be less than $5.1 billion.

What's changed since 2002:
  • Scope: Project limits are smaller.
  • Schedule: Begin-construction range has been delayed up to 1 year.
  • End-construction range has been accelerated 2 years.
  • Costs: Costs have gone down approximately $1 billion due to scope revisions.
  • Risk management: Identifying new strategies for improved environmental clearances and right-of-way processes. Coordinating decision strategies with FHWA.
Financial fine print (key assumptions):
  • Full project funding becomes available in July 2005. State I-405 Nickel funds will roll over into this package.
  • Inflation escalation is to 2010, the approximate midpoint of construction.
  • Additional Federal, State, regional, and local money may be needed.
  • Project cost range includes $18.5 million in past expense, beginning in 1999.
  • Assumes funding decisions do not interrupt or cause construction delays.
Level of project design:

low on a scale of low-medium-high.

July 16, 2006 Washington State Department of Transportation

Return to Text

Events

More Information

Contact

Hana Maier
Office of International Programs
202-366-6003
hana.maier@dot.gov

 
 
This page last modified on 11/15/07
 

FHWA
United States Department of Transportation - Federal Highway Administration