U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000


Skip to content
Facebook iconYouTube iconTwitter iconFlickr iconLinkedInInstagram

Office of International Programs

FHWA Home / Office of International Programs

Chapter 5: PPP Program Performance and Lessons Learned

Overall, PPPs have served the nations the scan team studied well. They have allowed them to achieve objectives they would not have otherwise. The countries, however, have had to learn hard lessons about these arrangements and endure intense scrutiny from other executive agencies, elected officials, and the public.

This chapter summarizes the outcomes achieved generally and by each country through the use of highway PPPs, as well as common lessons learned over the past two decades during their implementation.

Outcomes

PPPs have allowed all of the host nations to deliver specific projects sooner than possible with conventional project delivery methods. Essentially, the public sector's capacity to appropriate budgetary funds lags behind the private sector's ability to access capital in the financial markets, particularly for large-scale projects. Alone, this circumstance does not justify a PPP approach, but it is a fact that public agencies use to their advantage.

Several host nations claimed that PPPs produce better price and schedule certainty for design and construction. Certainly, one of the private partner's incentives is to open a project for service as quickly as possible so it can begin collecting revenue from tolls or government payments. As an illustration, table 10 shows the schedule performance of the PPP projects in New South Wales, Australia.

Portugal

Foremost, Portugal has built its National Motorway System using PPPs. In doing so, it has kept pace with the traffic demands of its country, vastly improved highway safety and travel times, and leveraged private investment. While upgrading the quality of the motorway system probably has more to do with the improvements in safety and travel times than the implementation of performancebased PPPs, the pace of Portugal's highway development program, and thus its improved motorway quality, is directly attributable to its aggressive PPP program since 2000. Figures 18 and 19 (see next page) are telling in this regard.

Spain

Similar to Portugal, Spain has built a majority of its National Highway System through concessions and, in the near future, will have more than half of this system under active PPP concessions. Since the 1960s, Spain has pioneered the concession model for infrastructure development and has continuously sought better ways to improve the effectiveness and efficiency of its approach. Along the way, it has also built a global industry that is positioned to provide highway development, operations, and financial services anywhere in the world.

Table 10. Schedule performance of highway PPPs in New South Wales.
ProjectOpenedScheduled OpeningTime Savings
M4May 1992Feb. 19939 months
M5Aug. 1992Feb. 199418 months
Sydney Harbour TunnelAug. 1992Aug. 1992On time
M2May 1997Nov. 19976 months
Eastern DistributorDec. 1999Aug. 20008 months
Cross-City TunnelAug. 2005Oct. 20052 months
Westlink M7Dec. 2005Aug. 20068 months
Lane Cove TunnelMar. 2007May 20072 months
Total53 months

This graph of traffic volume versus fatalities in Portugal shows that between 1985 AND 2005, TRAFFIC DEMAND INCREASED FOUR TIMES AND FATALITIES DECREASED BY HALF. THE LEFT VERTICAL AXIS IS MILLION VEHICLE-KILOMETERS TRAVELED FROM 10,000 TO 90,000. THE RIGHT VERTICAL AXIS IS FATALITIES FROM 0 TO 3,000. THE HORIZONTAL AXIS IS YEARS FROM 1980 TO 2004. TRAFFIC VOLUME RANGES FROM ABOUT 20,000 MILLION VEHICLE-KILOMETERS TRAVELED IN 1980 TO ABOUT 80,000 IN 2004. FATALITIES RANGE FROM ABOUT 2,300 IN 1980 TO ABOUT 1,100 IN 2004, PEAKING AT ABOUT 2,600 IN 1988. THE LINES FOR TRAFFIC VOLUME AND FATALITIES INTERSECT IN ABOUT 1998.
Figure 18. Traffic volume versus fatalities in Portugal.

This chart shows the decline in road fatalities per million inhabitants in Portugal between 1995 and 2006. In 1995, Portugal was at the top of the list of 25 European countries with 271 road fatalities per million inhabitants, 105 percent higher than the median rate of 132. In 2000, Portugal was third on the list with 184, 60 percent higher than the median of 116. In 2005, Portugal was 10th on the list at 119, 30 percent higher than the median of 91. In 2006, Portugal was 13th on the list at 91, 6 percent higher than the median of 86.
Figure 19. Road safety improvement in Portugal: 1995 to 2006.

Click image to enlarge

United Kingdom

PPPs, as well as increased use of the private sector in highway operations and maintenance contracts, have contributed to the Highways Agency's transition from a network provider to a network operator—"steering, not rowing." This has allowed the agency to heighten its awareness of its customers and focus on its key performance measures:

Australia

Australian states have used highway PPPs selectively in their urban centers to implement large-scale surface mobility improvements in a relatively short timeframe. These highways have improved both commuter and freight travel in the most densely populated cities in Australia—Sydney, Melbourne, and Brisbane. Similar to Spain, the activity in Australia has spawned an industry of highway developers, operators, and financiers. These private firms are also positioned to provide their services across the globe.

Common Lessons Learned

Preserving the Public's Interest While Attracting Private Participation

Over time, the host nations have learned that their highway PPP programs must preserve the public's interest and attract private participation. To some, these may be conflicting objectives. Balancing the two for PPP projects, however, essentially requires that the state and its citizens achieve the following:

Likewise, private participants require the following:

Previous sections of this report have highlighted various practices the nations visited use to facilitate these outcomes. For instance, public sector project and business case analysis methods help identify drivers of life-cycle value as well as appropriate risk-allocation strategies. Emphasis on project outputs enables public decisionmakers to pinpoint customer needs and target KPIs to satisfy those requirements. Competitive procurement processes (1) employ phased approaches to filter potential respondents down to a select few or (2) fix project requirements and bid parameters to improve transparency and accountability while driving down transaction costs. And the public sector's recognition that latent financial gains are possible in these sorts of arrangements precludes excessive private sector profits and promotes public confidence in government. Measures such as these prompt the private sector to focus its strengths on finding creative and effective solutions for complex projects.

Viewing Highway PPPs as Enterprises

Over time, the host nations have recognized that highway PPPs are enterprises that require a careful combination of technical, legal, and commercial conditions. This is fundamentally different from prescribing the requirements for a constructed facility, which is typically done in conventional project delivery. Instead, the public sector is granting the private sector the right to initiate and operate an enterprise within the bounds of a contract. Accordingly, a careful balance must be struck between the project's business and engineering provisions so that the private partner can succeed while also satisfying the public sector's objectives.

Building and Continuously Improving Public Sector Institutional Capacity

The host nations emphasized the importance of building and improving institutional capacity for PPP program effectiveness. From business case analysis through handback, PPPs present a variety of challenging tasks for public sector officials. As their PPP programs have matured and their staff capacity has increased, the host nations have relied less heavily on external consultants. This capacity has not been derived simply through experience. Rather, deliberate actions such as establishment of best practices groups, development of principles and guidelines, and creation of standard procedures have all contributed to this growth.13 Certainly, the need for complementary specialized expertise in areas such as legal and financial matters will not cease. However, the institutional infrastructure required to conceptualize, procure, deliver, and manage PPP arrangements as they themselves continue to evolve is significant. Failure to recognize this could leave a public agency overmatched by its private partner.

<< Previous Contents Next >>
Page last modified on November 7, 2014
Federal Highway Administration | 1200 New Jersey Avenue, SE | Washington, DC 20590 | 202-366-4000